Activity is in high gear at this project. Various speciality teams, appliance removal, cabenit removal, ceiling scraping, fixture removal, carpeting removal, are tackling the project simultaniously. Additionally, the window replacement and roof work has also started in earnest.
The plans calls for units to be done in ""Stairwells". From start to finish, each stairwell requires 20 days. Multiple stairwells will be worked on at the same time.
Originally, the developer planned to have only half of the project complete this year, with this renewed effort, the entire complex is now scheduled to be completed by mid November!!!!
First time home buyers will now have the luxury of getting into this project this year.